Huge concrete floor slab forms firm base for Tesco January 1st 2008 Specialist flooring contractor
Twintec Industrial Flooring
has completed what it
believes is the UK's biggest steel
fibre reinforced concrete floor slab
project for Tesco in Livingston.
Jointless SFRC floor slabs were
designed and constructed in the
ambient, chilled and freezer
warehouses, as well as the vehicle
maintenance unit and resource
recovery unit. The mining history of
the area required the ground under
the ambient slab to be suspended
on driven precast concrete piles.
Using a Twintec jointless SFRC
design, the team was able to
achieve a 75% reduction in the
amount of joints required and
thereby reduce opportunities for
joint breakdown and associated
costs and disruption.
The paving benefits from
improved ductility and the reduced
possibility of standing water is a
safety benefit.
Twintec chose to produce the
concrete itself, with batching
carried out by partner company,
Sitebatch Technologies using a
continuous mixing plant capable of
outputs to 70m3/h. This gave the
company total control of the entire
process. The delivery rate (in
excess of 600m3 of concrete per
day) to the work face suited the
fast track nature of the works.
All internal floor slabs were
specified as FM2 special (TR34 3rd
edition) and the company
describes the survey results as
outstanding. The tolerance has
been verified by independent floor
survey specialists and UKASaccredited
Face Consultants.
The project followed the Twintec
D-B-I formula (design, build,
insure) and was constructed by a
skilled workforce who laid almost
250 000m2 of concrete flooring
using 50 000m3 of concrete
incorporating 2000t of steel fibres,
contributing to a total project value
in excess of £7 million. |