Wizard solution to power supply July 1st 2007 Cable & Wireless says it has
improved the reliance of the
standby power system at its Dock
Street offices in London with the
support of integrated power
support company, Merlin Power
Management. Undertaken to
improve the resilience of the
emergency mains supply and
ensure sufficient reserve generator
capacity in the event of equipment
failure, Merlin Power engineered
and project managed the contract
from initial site survey through to
installation, commissioning, testing
and final handover. To best use the
generator capacity available, it was
decided that an existing 640kVA
genset would be moved by Merlin
Power from one of Cable &
Wireless' London offices and
relocated to the Dock Street facility.
Engineers then set about
synchronising the generator with
two other 640kVA generators
already on site; this involved the
design, manufacture and
installation of a new three-way
automatic synchronisation and
control system. More articles from Merlin Power Management: |