Fashion solutions May 1st 2007 Together HiLo-PSS Group and
AGF UK have enabled TNT
Fashion Group to continue
operations after a fire in November
2005 destroyed its warehouse in
Lutterworth, Leicestershire.
Supported by Planned Storage
Systems, a division of HiLo-PSS
Group, AGF racked a temporary
facility for TNT, then fitted out its
new storage facility.
PSS worked over a weekend to
equip the temporary building. To
house a diverse range of products,
it specified Stronglock adjustable
pallet racking.
PSS supplied racking and
shelving for the 36 900m2
temporary building and, when the
new building was ready, the
racking was dismantled and reerected
in the new facility.
AGF has made and fitted threetier
mezzanines in the site's two
new buildings, while PSS has
supplied 5000 frames, 47 000 pairs
of beams and 94 000 shelves.
Two installation teams started
work concurrently and TNT was
operational 14 weeks later. More articles from HiLo-PSS Group: |