Energy costs cut September 1st 2006 Powrmatic NV heaters and heat recovery units have improved heating performance, reduced energy costs and created extra space for Numatic at its manufacturing site in Somerset.
The NV heaters were installed in two phases. The first comprised four NV 120 heaters and 16 Calecon heat recovery units in a new manufacturing facility; the second comprised four NV 120 heaters and more Calecons as part of a refurbishment project.
Andrew Smith, head of manufacturing, says "The roof-mounted NV heaters have freed valuable floor space and transformed a cold building into a very comfortable working area." More articles from Powrmatic Ltd: |